Logistic path plan
Waterway
• Ships pontoon
• vessel size 32 mx 5 m
• carrying capacity of 50 Ton and 70 Ton
• Travel time is 2-4 days
• Rent a boat Rp. 60 million (incld. Power and unloading)
Strip overland
• Cars 4 WD and dump trucks
• For cars carrying capacity 4 WD 1.3 tons
• carrying capacity of 6-8 tonnes dump truck (dump truck smallest)
• Travel time 1- 2 days
• 4 wd car rental Rp. 8juta
• Rent dump trucks Rp. ..........
Constraints
• If the dry season, the water receded, the trip will be longer
• Power unloading at long bagun is a separate fee
• Required warehouse in long bagun
• Necessary transport equipment (forklift or the like)
Constraints
• Condition of roads in part already hardening, in part still land (50%: 50%)
• Condition of roads up and down. Lots rise and fall sharply.
• When the rainy season, travel time will be longer
• On the way, some time will cross the river without a bridge. If the rain will overflow rivers and fast-flowing. Have to wait until low tide to cross
• Several improvised bridge, to be very carefully through Supplementary information: - Rent a boat capacity of 40 tonnes of Rp 45 million - Rent a boat capacity of 70 tonnes of USD 63 million