Project evaluation is useful to reveal performance problems and provide feedback for improving the quality performance of the project in its implementation in order to reach the planned goals and objectives. Scheduling projects using network planning project acceleration results obtained during the 170 days of the initial plan is 175 days. Furthermore, the evaluation of the costs and time using three indicators in the analysis of variance approach so that the conclusions obtained from the calculation until week 25 that BCWS = USD 12,791,574.64 ACWP = USD 95,594,014.92 and BCWP = Rp 95,594,014.92 and CV = USD 0.00 and SV = USD 82,802,440.27 means to get the job done right on schedule at a lower cost than the budget.