PT KADI INTERNATIONAL informs about the excavation work above asphalt AC-BC (Photo attached) in the area around Main Road STA 0 + 00 which are not of our work, while we already have scheduled the execution of paving AIR CONDITIONING-WC included at that location.PT KADI INTERNATIONAL sought help from PT KIK to provide solutions to the above barriers where implementation of the work timetable paving is 5 (five) days, starting Saturday, date 5 August 2016