We inform the presence of iron we were already "on site" and we already manufacturing for the readiness of all work activities pembesian (Secondary Drain Type 24 and 25) we already carry out activities related to the material iron from start to delivery of materials from the date July 30, 2015 a number of 237.4 Ton (evidence attached), setting the iron and steel cutting we have carried out in August 2015 before rising official letter from Consulting PT LAPI Ganeshatama on temporary work stoppage on August 24, 2015. Therefore, we expect that the implementation of the work relating to material iron to be realized and can immediately diprogreskan. Here we enclose documentation material "on site" and the material that has been fabricated