2.1. GeneralThe purpose of the Detailed Engineering is to further develop and update the FEED study Asset Integrity Program – North Corridor (AIP-NC) for approved Approved for Construction status:• Having regard to the budget target of man-hour• Having regard to the work programme and schedule• Maximize team collaboration and minimizing re-employment• Nil accidents• Maximize productivityThe contractor will develop all the required engineering deliverable for the job and will send a Master Deliverables Register (MDR) to the company within two (2) weeks after the date the contracts effectively.The contractor shall verify, review and revise the status of the deliverable AFD engineering company provided where needed and will develop other deliverable is needed to carry out the work.The engineering team will prepare the final dossier of documentation including the final pictures of the US built and sent to the company in its original format and electronic format on CD.